Kitikmeot Corporation
 
 
 
 
 
 
Background
The Slave Geological Province has become one of the most widely known mineral exploration and development regions in the world. Known to host deposits of gold, copper, zinc, nickel, a nd now diamonds, this ancient rock is among the world's oldest and was formed about 2.7 to 2.5 billion years ago. The Slave Geological Province has produced much of the North's mineral wealth, most recently including such diamond mines as Ekati, Diavik, and even more recently, Tahera Diamond Mine (currently under construction). But the development of this area has been hindered by the remoteness and lack of transportation infrastructure. The development of an Arctic port and road network would foster mineral production in the Slave Geological Province, and would bring many long-term economic benefits to the Kitikmeot Region of Nunavut, as well as to Nunavut as a whole.
 
About the Proposed Road
Once constructed, the road will see trucks moving construction materials, as well as offshore fuel, to 'budding' mine sites, as well as to existing mine sites in the area. The project could slash the cost of getting supplies and fuel to these hard-to-reach areas. For example, materials for the Diavik mine are currently hauled overland 2,300 kilometers from Edmonton, by rail and across winter ice-roads. Shipping goods through the Arctic Ocean to Bathurst Inlet would be far cheaper, and the all-weather road would also lengthen the trucking season. The current trucking season is currently limited by ice conditions to only a few months in late winter. Access across Contwoyto Lake would be by ice road in the winter and barge in the summer. The project would have many spin-off benefits including reduced consumer costs in Kitikmeot communities through the provision of fuel and other bulk goods. The project will eventually be built through a 50-50 joint venture between Kitikmeot Corporation and Nuna Logistics, a majority-Inuit-owned company "renowned for its expertise in ice-road construction and transportation" (additional information regarding Nuna Logistics, in which Kitikmeot Corporation is a partner, is available on this website).
 
Chronology
April, 2000
An economic impact study was prepared for Kitikmeot Corporation by a team consisting of Professor Jack C. Stabler, Department of Agricultural Economics and Professor Eric C. Howe, Department of Economics, both of the University of Saskatchewan. The report projects the economic impact in Nunavut of the building of the road and port, as well as the economic impact of several mining projects impacted by the completion of the project. It projects the effect of the project on the GDP of Nunavut and Canada, as well as estimating the number of person-years of employment that will be created.
 
This report is available as a pdf file, by clicking here.
 
June, 2000
An important meeting of stakeholders was held in Cambridge Bay to prepare for the submission of funding applications to DIAND and the Government of Nunavut (GN).
 
Fall, 2000
Two committees were formed, also to help facilitate the above funding applications, as well as to provide oversight to the project operators. They were:
  Technical Advisory Committee - Chaired by Kitikmeot Corporation, and comprised of such organizations as Nuna Logistics, the Government of Nunavut, Hamlet of Kugluktuk, the Bathurst Inlet Port Committee, and others; and
  Project Management Committee - Chaired by the Kitikmeot Inuit Association. Comprised of a number of stakeholders including other municipalities, the Government of Nunavut, Federal representatives, and others.
 
July, 2001
Funding for a feasibility study of the project, at a total cost of $6 million, was approved. It was to be funded 50% by Indian and Northern Affairs, with 25% each from the Government of Nunavut, and various mining companies. The purpose of the feasibility study was to evaluate the cost of constructing and operating an all-weather toll roadway network and arctic port servicing known and potential users in the region. The primary focus of the study was the following transportation infrastructure:
  A port at the southern end of Bathurst Inlet capable of handling 50,000 ton vessels and ocean barges
  280 km of new all-weather gravel roads
  9 km of existing Lupin Mine roads, and
  69 km Contwoyto Lake ice road and summer barge route.
 
In July, 2001 engineers and environmentalists began studying a site at the southern end of Bathurst Inlet, where the construction of a deep-water port is planned. Researchers also scouted the route of the proposed all-weather road linking the port to Contwoyto Lake on the Nunavut-NWT border. At this time, the proposed route included Izok Lake, a zinc and nickel deposit 265 kilometers southeast of Kugluktuk.
 
December, 2001
The above study was completed by Nishi-Khon/SNC-Lavalin.
 
November, 2002
The Bathurst Road and Port project's original plan was for a 280-km all-weather road network, in two sections, connecting a sea-port at Bathurst Inlet with the huge Izok Lake mineral deposit. The first section will see a 210-km all-weather road stretching from the port to the eastern shore of Contwoyto Lake. The second section would extend to the Izok Lake property. However, about this time, Inmet dropped the Izok Lake property from its backers' immediate plans. The plan was thereby revised to include only the first phase, the 210-km stretch which would end at the shore of Contwoyto Lake. Inmet's decision was attributable to the price of base metal prices, which were quite low at the time, making development of the Izok deposit (and support for the road and port project) infeasible. Contradicting those who felt the exit of Inmet made the project uneconomical, it was pointed out that the Bathurst road and port's main purpose was not to build a transportation route to Izok Lake.
 
Rather, it was to stimulate economic development throughout the entire Kitikmeot Region, i.e. there are numerous other mineral deposits, and even operating mines, that will benefit from the development (thereby generating economic spin-offs for the Region). At this time, the Nunavut Impact Review Board was formally notified by the proponent of changes to the scope of the project, to exclude the Izok section of the road.
 

April, 2003

The Nunavut Impact Review Board (NIRB) advised the proponent that (as directed by the Minister of Indian Affairs) a revised project description was required, for the purposes of re-screening and re-submission (despite NIRB's stated opinion that the change may have the effect of reducing certain of the environmental impacts). At this time, a Part 6 panel review (as conducted by a Federal Environmental Assessment Panel) was being contemplated (as opposed to a Part 5 review, as conducted by NIRB).
 
May, 2004
Indian and Northern Affairs decided the project would undergo a territorial environmental review (Part 5 review, as described above), as opposed to a federal review (Part 6 review, as described above). The then Minister of Indian Affairs, Andy Mitchell, asked that the board pay special attention to the impact of the road and port project on the economy, as well as on the Region's wildlife.
Currently

The Environmental Impact Statement (EIS) for this project was submitted to the Nunavut Impact Review Board (NIRB) in late 2007, however was later put on hold primarily due to OZ Minerals' indication that they may build their own road from Izok north to the coast, following a different route.

Subsequently OZ Minerals indicated their support for BIPAR, however on June 11th, 2009, China Minmetals Corporation completed the acquisition of OZ Minerals, also indicating their support for BIPAR. As such, all indications are that NIRB will be asked to continue with their review of the project. And it is expected/hoped that Minmetals will elaborate on their previously indicated support for BIPAR in the near future.

 

More information on this project is available on the project website, at http://www.bipr.ca/

 

Supplementary information is also available on Nuna Logistics' website, at http://www.nunalogistics.com/projects/clients/bathurst/index.html

 
Proposed Road (Also Showing Izok Extension)
 
Artists Rendition of the Road & Port Project